Lakeshore Drive update

HOUGHTON — Hebert Construction is performing the last of their digging and installing of pipe in Huron Street near the Suomi Restaurant. This should be finished in about a week.

After they are done with installing the pipe, the sidewalks can be poured. This should also take a week.

When the sidewalks are poured, Payne and Dolan can finish the paving. This should take a week.

The project is scheduled to wrap up this month. All of this work is weather dependent — so hopefully the rain will stop for a few weeks so they can finish.