Graham Jaehnig/Daily Mining Gazette Houghton County Commissioner Roy Britz reviews documents during Tuesday's county board meeting in Houghton. Britz introduced a motion directing Traverse Engineering Services to inspect the leaking roof at the Houghton County Jail and provide an updated repair estimate.

HOUGHTON -- Last week, the Houghton County Board of Commissioners voted to re-engage Traverse Engineering Services to inspect the leaking roof at the Houghton County Jail and provide an updated cost estimate for repairs.

Commissioner Roy Britz introduced the request, noting the roof has leaked for roughly 15 years and conditions inside the facility have worsened while a previous repair plan sat on hold during recent jail millage proposals.

“A few years ago, we met with Traverse Engineering and looked at the roof that’s been leaking for probably 15 years,” Britz said. “They came up with a plan to put a second roof on, but that was put on hold because of the jail proposal going forward. As of now, the jail has sprung more leaks and it’s very detrimental to the building and the occupants.”

Traverse Engineering Services, based in Hancock, completed preliminary design work and specifications for the roof in 2023, Britz adding a return to the same firm avoids duplicating prior engineering expenses.

“They’ve already done all the legwork on this,” Britz said. “It would save us money on the engineering side to come up with an engineer’s estimate to move forward and get this done.” The issue of the roof needing replacement is not new. The Daily Mining Gazette reported in February that during a Jan. 29 meeting of the Sharon Avenue and Jail Property Use Committee, Britz noted the current membrane and gravel roof was installed in April 2015 and said an earlier inspection found small trees growing on top of the structure.

During that meeting, Britz said he recalled a time when water leaked into one of the holding cells through a light switch on the wall, posing a real danger to any inmate in the cell. The water came from a pipe inside the masonry wall. Repairing the pipe would require demolishing part of the wall, he said, but due to state regulations, any demolition would then require the entire building be brought up to state Dept. of Corrections code.

Houghton County Building Official Todd LaRoux told commissioners Tuesday that he has already contacted Traverse Engineering and obtained the 2023 preliminary drawings, adding that the work primarily involves finalizing those plans.

“There is roughly about 44 holes up there from all the ventilation that’s on top of it,” LaRoux said. “When the engineer and all of us looked at it, it didn’t make sense to try to patch that with the ventilation, insulation beyond its lifespan and all of the holes.”

Under the 2023 preliminary plan, contractors would construct a new roof above the existing structure while keeping the ventilation equipment on the exterior.

Board Chairman Tom Tikkanen said the board’s action authorizes LaRoux to follow up with Traverse Engineering to obtain pricing for finalizing the engineering plans.

Britz also asked that the firm evaluate the underlying roof structure for potential water damage accumulated over the past 15 years, noting that buckets were placed throughout the courthouse and jail shortly after the previous roof and exterior air-handling penetrations were installed.

Britz moved to direct Traverse Engineering to inspect the building and roof structure and provide a cost estimate. Commissioner Gretchen Janssen supported the motion, which passed.